Overseas Project - Civil

Roads and Bridges

Southern Transport Development Project Highway Section from Kurundugahahetekma to Matara, SRI LANKA

Roads and Bridges

On Going
Client: Road Development Authority of Sri Lanka
Project Outline: Construction of 29km long expressway, 5km access road and 16 nos. bridges.

Route 8 Eagle's Nest Tunnel, HONG KONG

Route 8 Eagle's Nest Tunnel, HONG KONG

Completed in 2007
Client: Highways Department of Hong Kong
Project Outline: Construction of 2.1km long 3-lane expressway twin tunnel with 0.4km long ventilation adit, 0.5km long tunnel approach,3nos portal buildings and 3-storey administration building.

Gampola Bridge and Muwagama Bridge, SRI LANKA

Gampola Bridge and Muwagama Bridge, SRI LANKA

Completed in 2003
Client: Road Development Authority of Sri Lanka
Project Outline: Construction of 2 nos. road bridge comprises 99m long 11.4m wide 3-span PC girder concrete Gampola Bridge and 99m long 11.4m wide 1-span steel trussed langer style arch Muwagawa Bridge.

Baseline Road Project II, SRI LANKA

Baseline Road Project II, SRI LANKA

Completed in 2002
Client: Road Development Authority of Sri Lanka
Project Outline: Construction of 3.2km long carriageway with 1 no. 32m long precast concrete bridge.

Baseline Road Improvement and Extension, SRI LANKA

Baseline Road Improvement and Extension, SRI LANKA

Completed in 2000
Client: Road Development Authority of Sri Lanka
Project Outline: Improvement of 4.7km long carriageway with 2 nos. precast concrete beam bridges, and 1 no. box culvert bridge.

Road and Tunnel Link at Discovery Bay North, HONG KONG

Road and Tunnel Link at Discovery Bay North, HONG KONG

Completed in 2000
Client: Hong Kong Resort Co., Ltd.
Project Outline: Construction of 2.4km long dual lane highway and 628m long dual lane road tunnel, completed with 2 nos. of bridges and associated building.

National Highway No.1A Project, VIETNAM

National Highway No.1A Project, VIETNAM

Completed in 2001
Client: Ministry of Transport and Communications
Project Outline: Construction of total 94km long carriageway comprises 40km long carriageway (17km new road, 23km improvement) with 1 no. bridge in Phase 1 and 54km long (23km new road, 31km improvement) with 5 nos. bridges in Phase 2.

The Second Highway Rehabilitation Project, VIETNAM

The Second Highway Rehabilitation Project, VIETNAM

Completed in 2001
Client: Ministry of Transport and Communications
Project Outline: Construction of total 128km carriageway comprises 45km long carriageway with 3 nos. bridges in Phase 3 and 83km long carriageway with 3 nos. bridges in Phase 4.

Western Harbour Crossing, HONG KONG

Western Harbour Crossing, HONG KONG

Completed in 1997
Client: Western Harbour Tunnel Co., Ltd.
Project Outline: Design and construction of 1,362m long dual 3 lane immersed tube tunnel completed with 638m cut & cover tunnel.