Chubu Electric Power, Tokuyama Hydroelectric Power Station
Orderer | Chubu Electric Power Co., Inc. |
---|---|
Completion | 2015 |
Structure and scale | Cross section method, excavation cross-section: 19m²; tunnel length: 2,104m |
Location | Gifu Prefecture |
Application | Headrace tunnel |
A large-scale general hydroelectric power station was constructed that generates 161,900kW by intaking up to 100.4m³/s of water from the selective withdrawal intake of the Tokuyama Dam that Kumagai Gumi was responsible for the construction of. Unit 1 generates power in response to peak demand, and Unit 2 constantly generates power using the water required directly downstream of the Tokuyama Dam.